Tunnel Jumeirah Palm Island, United Arab Emirates

Données projet

Adresses: Dubai, Émirats arabes unis

  • length of tunnel: 996 m
  • total length: 1.4 km
  • width/ height of cross-section: 38 m / 9.16 m
  • structure: tunnel in open-type construction with separate casting method, three-cell rectangular cross-section

Exigences projet

  • 25 m long concreting sections
  • fabrication of bottom plate, two shear walls and slab after each other

Client

Al Naboodah Engineering Services L.L.C., Dubai

Avantages pour le client

  • fast cycle sequences
  • easy handling
  • versatile utilisation
  • application of 200,000 m³ of concrete in a construction time of only 11 months
Tunnel Jumeirah Palm Island Statement: Walter Freitag, Construction Manager
Walter Freitag
Construction Manager

We were able to achieve a fast cycle sequence with the PERI systems. They are easy to handle and offer many different uses. On top of this, PERI offered us the required technical support at the jobsite.

Solutions PERI

  • tunnel formwork solution from system components